A strategy designer at a semiconductor distributor is about to build alignment with a group whose position on the project is unknown. What should be done before designing the alignment activities?
選択肢
- Schedule a single large session so that everyone hears the same thing at once.
- Prepare a standard set of alignment materials that can be used with any audience, so that the same message reaches every group and no one gets a different version.
- Ask the executive sponsor to state publicly that the project has their backing, so the group understands the work is a priority.
- Assess the starting point by understanding each person's motivations, goals, and feelings about the work, drawing on the internal research already collected.