問題文
The station model has the driving path at zero float and eleven other paths between one and four days of float. The plan says which of those the scheduler must watch. What decides it?
選択肢
- Deciding which other paths get watched uses the proximity cutoff that the plan wrote down in advance, and each watched path is then given the individual line that the reporting arrangements require.
- Deciding which other paths get watched uses the alphabetical cutoff that the plan wrote down in advance, and each watched path is then given the individual line that the reporting arrangements require.
- Deciding which other paths get watched uses the proximity cutoff that the plan wrote down in advance, and each watched path is then given the pooled line that the reporting arrangements require.
- Deciding which other paths get watched uses the alphabetical cutoff that the plan wrote down in advance, and each watched path is then given the pooled line that the reporting arrangements require.