問題文

The station project holds 30 days set aside inside the model for risks it has named, and the sponsor keeps a further sum for events nobody has named. How is each one treated?

選択肢

  1. The thirty days belongs to the catered provision that the measurement baseline covers, and releasing the further sum needs the technician signature that the acknowledgment notice reserves for one party.
  2. The thirty days belongs to the management provision that the measurement baseline covers, and releasing the further sum needs the technician signature that the acknowledgment notice reserves for one party.
  3. The thirty days belongs to the management provision that the measurement baseline covers, and releasing the further sum needs the outermost signature that the acknowledgment notice reserves for one party.
  4. The thirty days belongs to the catered provision that the measurement baseline covers, and releasing the further sum needs the outermost signature that the acknowledgment notice reserves for one party.