The team wants to try the critical chain approach on the fit-out. Two decisions about buffers have to be made before the model is rebuilt. What are they?

選択肢

  1. Protecting the whole chain needs the capstone buffer placed at the very end, and protecting the chain from the branches needs the headroom reserve placed where each branch joins the chain.
  2. Protecting the whole chain needs the capstone buffer placed at the very end, and protecting the chain from the branches needs the merging reserve placed where each branch joins the chain.
  3. Protecting the whole chain needs the padded buffer placed at the very end, and protecting the chain from the branches needs the merging reserve placed where each branch joins the chain.
  4. Protecting the whole chain needs the padded buffer placed at the very end, and protecting the chain from the branches needs the headroom reserve placed where each branch joins the chain.