During deployment at a parking operator, the engineering group says five features must be cut to launch on time. How should the strategy designer contribute?
選択肢
- Offer a compromise informed by which cuts hurt the user least, for example fewer cuts with a reduced form of one feature rather than removing it outright.
- Insist that the full scope ships, since the vision was agreed months ago.
- Ask leadership to move the launch date so that the whole scope can be delivered, on the grounds that a partial release proves little.
- Accept the engineering assessment as given, since the delivery team is closest to the effort involved and can judge best.