A logistics firm's project manager wants to understand the normal order of activities in an integration project so she can plan the schedule. Which sequence reflects the typical lifecycle?
選択肢
- Deploy to production first, then design the APIs, then discover what the business actually needed, and only at the end build the applications.
- Build all of the code, ship it to production, and skip both the design and the testing stages because they only slow the delivery date down and add cost.
- Operate and monitor an empty environment first, then discover the requirements, and never deploy anything at all.
- Discover the requirements, design the APIs, build and test the applications, deploy them, and then operate and monitor them.