問題文
A business analyst is explaining to a new team member how scope, requirements, and user stories relate to each other. Which explanation is correct?
選択肢
- Scope sets the boundary of what will be addressed, requirements state what has to be true inside that boundary, and user stories express those requirements in a form a delivery team can pick up and finish.
- Requirements are written first, and scope is what they add up to, so the boundary of the project is established by collecting every requirement anyone raises.
- User stories are the detailed version of requirements, requirements are the detailed version of scope, and each layer is a complete restatement of the layer above it in more words.
- They are three names for the same information at different times in the project: scope is the discovery name, requirements the analysis name, and user stories the delivery name.