What does it mean for a user story to be ready for development to pick up?

選択肢

  1. The story has been approved by the sponsor and recorded in the repository with a link to the requirement it came from.
  2. The need, the person who has it, and what has to be true for it to be satisfied are all clear enough that the team can start without waiting for an answer.
  3. Every question that could possibly arise during the build has been anticipated and answered in advance, so the team needs no further contact.
  4. The story has been estimated by the team, because an estimate is what shows the story is understood well enough.