A business analyst has listed 22 stakeholders for a project at a food producer. What is the most useful way to use that list when planning how much time to spend with each of them?

選択肢

  1. Separate those whose decisions can change the project from those who are affected by it but decide nothing, and plan a different kind of contact for each.
  2. Ask the sponsor to reduce the list to a manageable number that can be brought together in one room to reach decisions.
  3. Rank all 22 by seniority and allocate time from the top down, because the most senior people have the broadest view and can answer questions about several areas at once.
  4. Interview all 22 for the same length of time so that nobody feels excluded and no group can question what attention it was given.