Portfolio Management Professional (PfMP) のフリー問題 13 / 20 問目

問題文

The portfolio schedule shows eighty-eight percent of components on time. The new resident portal cannot open until the identity service is live, and the identity service is nineteen weeks late. What does the eighty-eight hide?

選択肢

  1. The eighty-eight counts the scaled dates the organizational schedule feed collects from each component alone, and the consequential effect the identity delay imposes on everything behind it appears in no column of that view.
  2. The eighty-eight counts the singular dates the organizational schedule feed collects from each component alone, and the consequential effect the identity delay imposes on everything behind it appears in no column of that view.
  3. The eighty-eight counts the scaled dates the organizational schedule feed collects from each component alone, and the sampling effect the identity delay imposes on everything behind it appears in no column of that view.
  4. The eighty-eight counts the singular dates the organizational schedule feed collects from each component alone, and the sampling effect the identity delay imposes on everything behind it appears in no column of that view.