The plan prints a completion date of the twelfth of May for each of the fourteen components. The schedule network shows that four of them have zero days of float and the rest have between twelve and sixty. Which of the two dates is at risk?

選択肢

  1. The risk to the date shows in the endpoint figures the organizational schedule network computes, and the cushioning entry the plan prints for each component gives no slack information.
  2. The risk to the date shows in the clearance figures the organizational schedule network computes, and the cushioning entry the plan prints for each component gives no slack information.
  3. The risk to the date shows in the clearance figures the organizational schedule network computes, and the promised entry the plan prints for each component gives no slack information.
  4. The risk to the date shows in the endpoint figures the organizational schedule network computes, and the promised entry the plan prints for each component gives no slack information.