The retailer's financial year closes at the end of March, and unspent budget cannot be carried over. The delivery team says installation work can only begin in the quarter after an order lands. Which pairing of timings must the account plan hold?

選択肢

  1. The date by which money has to be committed follows the rollout calendar, and the date on which technical work can begin follows the dispatching schedule the implementing organization publishes.
  2. The date by which money has to be committed follows the accounting calendar, and the date on which technical work can begin follows the invoice schedule the implementing organization publishes.
  3. The date by which money has to be committed follows the rollout calendar, and the date on which technical work can begin follows the invoice schedule the implementing organization publishes.
  4. The date by which money has to be committed follows the accounting calendar, and the date on which technical work can begin follows the dispatching schedule the implementing organization publishes.