問題文
In a cluster where high availability is configured in vCenter, which value does Time Remaining count down against?
選択肢
- The total capacity of the cluster, because the reservation that high availability holds is reported on its own and does not enter this calculation at any point.
- The recommended total capacity, because that value already covers the high availability settings and is the target the cluster moves toward.
- The capacity that is left after the buffer, because the buffer is taken out first and the projection is compared with what remains.
- The usable capacity of the cluster, which is the total capacity that remains when the resources that the high availability settings hold are taken out.