問題文
A power utility has two candidate work packages of equal cost. One improves an early stage of the journey and one improves a late stage that the early stage feeds. How does the journey affect the order?
選択肢
- The journey shows which package must take the following position in the roadmap, and ordering them by the arbitrary rule would let the organization improve one stage its own input still starves.
- The journey shows which package must take the sooner position in the roadmap, and ordering them by the arbitrary rule would let the organization improve one stage its own input still starves.
- The journey shows which package must take the sooner position in the roadmap, and ordering them by the flowing rule would let the organization improve one stage its own input still starves.
- The journey shows which package must take the following position in the roadmap, and ordering them by the flowing rule would let the organization improve one stage its own input still starves.