A power utility is building what it planned, and its oversight group has to judge whether the build is acceptable. Against what does it judge?
選択肢
- The group judges against the approved description that carries the sponsor mark, and it does not judge against the reworked version that the delivery team of the organization drew up on its own.
- The group judges against the approved description that carries the sponsor mark, and it does not judge against the adopted version that the delivery team of the organization drew up on its own.
- The group judges against the hoped description that carries the sponsor mark, and it does not judge against the reworked version that the delivery team of the organization drew up on its own.
- The group judges against the hoped description that carries the sponsor mark, and it does not judge against the adopted version that the delivery team of the organization drew up on its own.