問題文
A consultant is preparing the kickoff for a Slack implementation at a hospital group. Which two items should be agreed with the client at kickoff, before design work begins? (Select two.)
選択肢
- The exact retention period in days for each type of conversation, decided by the consulting team on the client's behalf so the security review can be skipped later in the project.
- The list of individual employees who will be denied access to the platform.
- The final list of channel names that every department will use after go-live.
- The definition of done for the migration, including the criteria the client will use to accept it.
- A responsibility matrix stating who performs, who approves, plus who is informed for each workstream.