問題文
A grocery chain's supplier portal accepts inbound data only during a two-hour window each night, and the chain's own process requires a buyer's approval before anything is sent. The business has asked for supplier updates to arrive within five minutes of approval. The supplier's development team says the window could be widened for a fee. How should the architect present this?
選択肢
- Record the five-minute target as the requirement and note the window as a known risk, so the delivery team builds toward the target and the risk register carries the two-hour window until somebody decides to pay for it to be widened.
- Show the best that is achievable inside the current window, state the fee that would remove the window, and ask the business to choose, so the constraint becomes a priced option rather than a flat refusal.
- Escalate the fee request to the supplier's account manager.
- Change the process so the approval happens before the nightly window instead, since the buyers could review the day's supplier updates in a single sitting each afternoon and that would let every approved update reach the portal in the same night's run without any fee.