A release to production contains Apex classes. The team has not specified which tests to run. What happens, and what is the consequence for the release window?
選択肢
- Only the tests for the classes in the payload run, and the release window can therefore be planned from the number of classes the deployment contains.
- All tests in the org run except those that come from installed packages, so the window must allow for the full local suite.
- Every test in the org runs, including the tests that belong to installed packages, which makes the window unpredictable because the customer does not control how long a vendor's tests take to execute.
- No tests run unless they are named, so the deployment completes as quickly as the components can be created, and the team can run the suite afterwards at a time of its choosing to confirm that nothing was broken by the release.