問題文
A blade has to be sent back and a replacement will be fitted in the same bay a few days later. The engineer has to say what must be true of the rest of the system before the blade leaves, and what the system does once the replacement is in. Which pair states those two things?
選択肢
- The blade leaves now and returns later, so the remaining space absorbs the released occupancy and the finished rebuild restores the lost redundancy in that documentation.
- The blade leaves now and returns later, so the remaining space absorbs the released occupancy and the finished rebuild restores the lost availability in that documentation.
- The blade leaves now and returns later, so the remaining space absorbs the released allocation and the finished rebuild restores the lost redundancy in that documentation.
- The blade leaves now and returns later, so the remaining space absorbs the released allocation and the finished rebuild restores the lost availability in that documentation.