問題文
A customer schedules their own upgrade through the self-service path. The check that runs first has found a problem, and the customer wants to know whether the window they booked still holds. Which pair states what happens to each?
選択肢
- The customer drives the run without the vendor, so the failed pre test stops the run at sequencing and the chosen start follows the booked cadence in that implementation.
- The customer drives the run without the vendor, so the failed pre test stops the run at staging and the chosen start follows the booked cadence in that implementation.
- The customer drives the run without the vendor, so the failed pre test stops the run at sequencing and the chosen start follows the booked schedule in that implementation.
- The customer drives the run without the vendor, so the failed pre test stops the run at staging and the chosen start follows the booked schedule in that implementation.