PMI Scheduling Professional のフリー問題 13 / 20 問目

問題文

One subcontractor sends nothing by the cutoff. The scheduler must still publish the update tomorrow. What goes into the model for that firm?

選択肢

  1. The line for that firm carries the concocted position that the model held before, and the gap is recorded as the absent status that the certification docket shows beside the published dates.
  2. The line for that firm carries the earlierset position that the model held before, and the gap is recorded as the absent status that the certification docket shows beside the published dates.
  3. The line for that firm carries the earlierset position that the model held before, and the gap is recorded as the accepted status that the certification docket shows beside the published dates.
  4. The line for that firm carries the concocted position that the model held before, and the gap is recorded as the accepted status that the certification docket shows beside the published dates.