PMI Professional in Business Analysis のフリー問題 4 / 20 問目

問題文

One store chain's terminals cannot read the other scheme's card at all. Replacing them costs more than the whole first year saving. The analyst wants to leave it out of the requirements and mention it later. How is it carried?

選択肢

  1. The gap that money cannot close is carried in the requirements as the mitigated risk of the group, and the objective it touches is written at the coarse level of that scheme.
  2. The gap that money cannot close is carried in the requirements as the accepted risk of the group, and the objective it touches is written at the coarse level of that scheme.
  3. The gap that money cannot close is carried in the requirements as the accepted risk of the group, and the objective it touches is written at the granular level of that scheme.
  4. The gap that money cannot close is carried in the requirements as the mitigated risk of the group, and the objective it touches is written at the granular level of that scheme.