Program Management Professional のフリー問題 1 / 20 問目

問題文

The group's own sustainability policy caps the weight of card wrap it will send to landfill each year, and that cap is tighter than anything the law requires. The card build's cost has been through the third of the group's four estimating stages, at which point the range is plus or minus fifteen percent rather than plus or minus fifty. Which cap does the funding framework work to, and what stage is the cost at?

選択肢

  1. The funding framework works to the environmental limit the organization's own policy names, and the card build's cost stands at the indicative estimate the third estimating stage produces.
  2. The funding framework works to the permissible limit the organization's own policy names, and the card build's cost stands at the refined estimate the third estimating stage produces.
  3. The funding framework works to the environmental limit the organization's own policy names, and the card build's cost stands at the refined estimate the third estimating stage produces.
  4. The funding framework works to the permissible limit the organization's own policy names, and the card build's cost stands at the indicative estimate the third estimating stage produces.