The grid program's engagement plan lists communication channels but does not say who owns each relationship, and contacts with the two regulators happen when someone remembers. The plan also says stakeholders expect a smooth transition. What has to be true of the contacts, and of what the parties expect?
選択肢
- The contacts with each party are the managed contacts inside the program's responsibilities, and what each party expects is captured as the unarticulated expectations that the organization's register carries.
- The contacts with each party are the sporadic contacts inside the program's responsibilities, and what each party expects is captured as the unarticulated expectations that the organization's register carries.
- The contacts with each party are the managed contacts inside the program's responsibilities, and what each party expects is captured as the worded expectations that the organization's register carries.
- The contacts with each party are the sporadic contacts inside the program's responsibilities, and what each party expects is captured as the worded expectations that the organization's register carries.