Program Management Professional のフリー問題 5 / 20 問目

問題文

The grid program's board approved the change to the metering specification, and the schedule was updated the same day. The benefit register still carries the old saving, the risk register still carries the risk the change removes, and the component manager who asked for it has heard nothing. What must be true of the updates, and what state must that manager be left in?

選択肢

  1. Approving the change to the specification leaves the registers holding the inconsistent updates that the organization enters that day, and it leaves the manager who asked as the uninformed requester that the record shows.
  2. Approving the change to the specification leaves the registers holding the complementary updates that the organization enters that day, and it leaves the manager who asked as the notified requester that the record shows.
  3. Approving the change to the specification leaves the registers holding the inconsistent updates that the organization enters that day, and it leaves the manager who asked as the notified requester that the record shows.
  4. Approving the change to the specification leaves the registers holding the complementary updates that the organization enters that day, and it leaves the manager who asked as the uninformed requester that the record shows.