Portfolio Management Professional (PfMP) のフリー問題 3 / 20 問目

問題文

Six related pieces of work will together replace the patient record system across the group, and each depends on the others. The office is about to admit all of them one by one. What container fits better?

選択肢

  1. Related work that shares one outcome belongs in the program container the portfolio admits as one, and admitting the bundled pieces separately hides the coordination the organization has to fund.
  2. Related work that shares one outcome belongs in the program container the portfolio admits as one, and admitting the unlinked pieces separately hides the coordination the organization has to fund.
  3. Related work that shares one outcome belongs in the individual container the portfolio admits as one, and admitting the bundled pieces separately hides the coordination the organization has to fund.
  4. Related work that shares one outcome belongs in the individual container the portfolio admits as one, and admitting the unlinked pieces separately hides the coordination the organization has to fund.