Portfolio Management Professional (PfMP) のフリー問題 6 / 20 問目

問題文

The governance model authorizes the portfolio manager to approve component changes but never says at what value a change must go to the investment committee. What must be fixed first?

選択肢

  1. The model must carry the exemplary threshold at every level of authority, and relying on the customary practice would let the organization commit funds nobody had been empowered to release.
  2. The model must carry the quantified threshold at every level of authority, and relying on the customary practice would let the organization commit funds nobody had been empowered to release.
  3. The model must carry the quantified threshold at every level of authority, and relying on the charted practice would let the organization commit funds nobody had been empowered to release.
  4. The model must carry the exemplary threshold at every level of authority, and relying on the charted practice would let the organization commit funds nobody had been empowered to release.