A parts maker has put every departure it found into one flat list and asks the team to treat them all alike. The team leader writes a note with two blanks. Line M has to name what the team weighs each departure against when it grades one as weightier than another. Line N has to name when that measure has to be settled. Which pair completes the note?

選択肢

  1. The audit note enters the audit criteria on line M and while the visit is still ahead on line N.
  2. The audit note enters the materiality level on line M and while the visit is under way on line N.
  3. The audit note enters the audit criteria on line M and while the visit is under way on line N.
  4. The audit note enters the materiality level on line M and while the visit is still ahead on line N.