A team on the resource allocation platform has an assigned share of eight accelerators. A member wants a long training run that will not be stopped part way. Which submission fits, given how the platform hands out resources?
選択肢
- Request more than the share and mark the work as one that must not be interrupted, which is exactly what protects it from being reclaimed later when another project starts asking for the resources it is currently borrowing.
- Request more than the share and accept interruption, since a long run benefits most from extra capacity.
- Raise the work's priority above the others, which prevents reclamation.
- Keep the request inside the team's assigned share and mark the work as one that must not be interrupted, since resources beyond the share are only lent to work that can be stopped.