問題文
A company must run one large training campaign in the next two months and does not know whether similar campaigns will follow. Procuring hardware would take most of that time. Which approach fits, and why?
選択肢
- Rent accelerated capacity for the campaign, because the need is short and uncertain and the lead time for hardware does not fit.
- Run the campaign on the existing general purpose servers, since the workload is just arithmetic.
- Postpone the campaign until the procurement completes, because mixing environments is not supported and the schedule can absorb the delay.
- Buy the hardware anyway and start the campaign late, because owning equipment is always less expensive over its lifetime than renting the same capacity for any period.