A team commits to a fixed scope, a fixed deadline and a fixed budget simultaneously. What does this leave as the only remaining variable?
選択肢
- Quality, which will absorb the pressure unless one of the other three is allowed to move.
- The size of the team, and it can be increased so that the same scope is finished inside the fixed deadline.
- Nothing, because a project with all three fixed is fully determined and the team's task is simply to execute the plan as it was agreed, which is why this arrangement is considered the clearest form of commitment.
- The choice of technology, and the team can still change in order to fit the work into the time and the money agreed.