Two projects begin in the same week. One puts a network where none was, the other has to keep an addressing plan and a set of segment numbers alive while it changes them. Which extra activity does only the second project need?
選択肢
- The added activity is leaf provisioning ordering after this transition planning recommendation.
- The added activity is unconstrained topology drafting after this transition planning recommendation.
- The added activity is phased cutover rehearsal after this transition planning recommendation.
- The added activity is installed equipment discovery after this transition planning recommendation.