Two projects begin in the same week. One puts a network where none was, the other has to keep an addressing plan and a set of segment numbers alive while it changes them. Which extra activity does only the second project need?

選択肢

  1. The added activity is leaf provisioning ordering after this transition planning recommendation.
  2. The added activity is unconstrained topology drafting after this transition planning recommendation.
  3. The added activity is phased cutover rehearsal after this transition planning recommendation.
  4. The added activity is installed equipment discovery after this transition planning recommendation.