A tester applies all-path coverage to an activity diagram of a claims workflow that contains three loops. The generator runs overnight and produces more than forty thousand test cases, which the project cannot execute. Which option names what happened and the remedy the syllabus gives?
選択肢
- Pure combinatorial generation caused a test case explosion, so the team should adapt the execution schedules and apply intelligent failure records.
- Pure combinatorial generation caused a test case explosion, so the team should adapt the hardware resources and apply intelligent cloud machines.
- Pure combinatorial generation caused a test case explosion, so the team should adapt the modeling guidelines and apply intelligent review checklists.
- Pure combinatorial generation caused a test case explosion, so the team should adapt the generation strategies and apply intelligent filter mechanisms.