A test lead is drawing up the test plan for a project that will use model-based testing for the first time. She wants to list the activities that classic test analysis and test design do not already contain, so that the extra effort is visible in the plan. Which pair belongs on that list?

選択肢

  1. Confirming the entry conditions and publishing the summary dashboards, because those steps sit outside plain test analysis and plain test design.
  2. Renegotiating the release windows and scheduling the coordinated deployments, because those steps sit outside plain test analysis and plain test design.
  3. Assessing the remaining effort and reporting the weekly status, because those steps sit outside plain test analysis and plain test design.
  4. Building the model elements and deriving the test cases, because those steps sit outside plain test analysis and plain test design.