問題文
Two things happen on the same morning: a dashboard is refreshed with the overnight defect trend, and the team decides to postpone one story and start an exploratory session instead. Which option names the two activities correctly?
選択肢
- The nightly execution performs the test monitoring, and the recorded defect performs the test control that the separate department decides
- The typeset summary performs the test monitoring, and the verbal handover performs the test control that the formal committee decides
- The refreshed dashboard performs the test monitoring, and the changed plan performs the test control that the entire team decides
- The changed plan performs the test monitoring, and the refreshed dashboard performs the test control that the external manager decides