A team receives a one-line request from a new stakeholder and starts coding the next morning. Which requirements engineering activity does the syllabus place first here, and what does practicing it continuously produce?

選択肢

  1. Requirements specification captures the written statement, so the semiformal model progressively produces the precise document before the iteration ends
  2. Requirements elicitation captures the stakeholder need, so the collaborative workshop progressively produces the testable story before the iteration ends
  3. Requirements analysis captures the hidden conflict, so the prioritized list progressively produces the feasible outcome before the iteration ends
  4. Requirements validation captures the complete criterion, so the early review progressively produces the consistent wording before the iteration ends