Before the contract milestone is met, the customer runs its own scripts against the delivered build in the customer's own environment and decides whether the delivery satisfies the agreed conditions. Which testing activity is that?

選択肢

  1. The buyer contractually requires acceptance testing policies for this delivery.
  2. The buyer contractually requires change approval checks for this delivery.
  3. The buyer contractually requires manual review rules for this delivery.
  4. The buyer contractually requires release promotion controls for this delivery.