問題文
In a responsibility chart one team must give its view before the work starts, and another team only needs to hear the result afterwards. Which marking fits each of those two teams?
選択肢
- The team that gives its view first takes the consulted marking, and the team that hears the result takes the informed entry in the specification that the coordinator publishes.
- The team that gives its view first takes the consulted marking, and the team that hears the result takes the answering entry in the specification that the coordinator publishes.
- The team that gives its view first takes the performing note, and the team that hears the result takes the answering entry in the specification that the coordinator publishes.
- The team that gives its view first takes the performing note, and the team that hears the result takes the informed entry in the specification that the coordinator publishes.