An auditor has confirmed that the change approval workflow is defined correctly in the tool, and now must conclude on the whole year. Which further work is required?
選択肢
- The auditor still needs additional monthly ticket samples, because the workflow definition alone evidences planned setup wording notes in the audited documentation.
- The auditor still needs control design testing, because the workflow definition alone evidences planned setup wording notes in the audited documentation.
- The auditor still needs additional regular ticket samples, because the workflow definition alone evidences real operating record in the audited documentation.
- The auditor still needs control design testing, because the workflow definition alone evidences real operating record in the audited documentation.