問題文
The cold store project has a fixed capital limit and a shutdown window of two nights for any work inside the chambers. Which pair states what the capital limit decides and what the shutdown window decides in the requirement?
選択肢
- The two constraints bite on different choices, so the capital limit caps the installed quantity and the shutdown window fixes the staged budgets in that specification.
- The two constraints bite on different choices, so the capital limit caps the installed quantity and the shutdown window fixes the staged sequence in that specification.
- The two constraints bite on different choices, so the capital limit caps the installed reach and the shutdown window fixes the staged budgets in that specification.
- The two constraints bite on different choices, so the capital limit caps the installed reach and the shutdown window fixes the staged sequence in that specification.