The installation is complete and the designer opens the management platform for the first validation step. Forty two units were ordered and fitted. What is checked here, before anybody walks the floors with an instrument?
選択肢
- The platform is read to confirm the reporting units, and the reading is compared against the tendered quantity the equipment schedule fixed before the order went out.
- The platform is read to confirm the reporting units, and the reading is compared against the amended quantity the equipment schedule fixed before the order went out.
- The platform is read to confirm the missing units, and the reading is compared against the tendered quantity the equipment schedule fixed before the order went out.
- The platform is read to confirm the missing units, and the reading is compared against the amended quantity the equipment schedule fixed before the order went out.