問題文
Two cost controls are written into the operating procedure after one team burned through the quarter's money in five weeks. The first is a number that says how much may be spent in a month before anything else happens, agreed with the finance side and recorded. The second says what the platform does to the callers of a team that has reached the number, so that the service is slowed rather than switched off. Which pair states what each control sets?
選択肢
- The two controls bound the same spend, so the monthly budget sets the agreed ceiling and the noisy tenant meets the timed replication in that documentation.
- The two controls bound the same spend, so the monthly budget sets the agreed ceiling and the noisy tenant meets the timed throttling in that documentation.
- The two controls bound the same spend, so the monthly budget sets the agreed commitment and the noisy tenant meets the timed replication in that documentation.
- The two controls bound the same spend, so the monthly budget sets the agreed commitment and the noisy tenant meets the timed throttling in that documentation.