The requirements are agreed and signed. Before anyone writes code, the utility has to decide how the meter, the gateway and the platform speak to each other, in what units and with what field names, so that two suppliers can build their halves separately. The architecture record has to name the phase and what it settles first. Which pairing belongs in the record?
選択肢
- The architecture record sets the design phase that this decision sits in, and the same record identifies the interface contract that the phase has to settle before coding.
- The architecture record sets the handover phase that this decision sits in, and the same record identifies the interface contract that the phase has to settle before coding.
- The architecture record sets the design phase that this decision sits in, and the same record identifies the delivery contract that the phase has to settle before coding.
- The architecture record sets the handover phase that this decision sits in, and the same record identifies the delivery contract that the phase has to settle before coding.