問題文
The agency has agreed on a twelve week study. At week four the team plans to show only that the fare files can be read and that a rough model runs at all, with no attempt to make it usable by staff. At week ten it plans to hand a small but genuinely usable tool to two station supervisors. What should the two dates be called?
選択肢
- The schedule records the week four output as the usability check and the week ten output as the finished product that two station supervisors exercise in their own office.
- The schedule records the week four output as the feasibility check and the week ten output as the minimal product that two station supervisors exercise in their own office.
- The schedule records the week four output as the usability check and the week ten output as the minimal product that two station supervisors exercise in their own office.
- The schedule records the week four output as the feasibility check and the week ten output as the finished product that two station supervisors exercise in their own office.