Certified Data Science Practitioner (CDSP) のフリー問題 2 / 20 問目

問題文

The agency has agreed on a twelve week study. At week four the team plans to show only that the fare files can be read and that a rough model runs at all, with no attempt to make it usable by staff. At week ten it plans to hand a small but genuinely usable tool to two station supervisors. What should the two dates be called?

選択肢

  1. The schedule records the week four output as the usability check and the week ten output as the finished product that two station supervisors exercise in their own office.
  2. The schedule records the week four output as the feasibility check and the week ten output as the minimal product that two station supervisors exercise in their own office.
  3. The schedule records the week four output as the usability check and the week ten output as the minimal product that two station supervisors exercise in their own office.
  4. The schedule records the week four output as the feasibility check and the week ten output as the finished product that two station supervisors exercise in their own office.